EcoTechnoPark: work on the cargo track

EcoTechnoPark: work on the cargo track

19 August 2016 5468

Our filming crew has just returned from EcoTechnoPark and now we would like to summarize the past working week. These weekend days will be days-off not for everyone, because the work on creating SkyWay technology in the design office, EcoTechnoPark and the experimental production facility goes on 24 hours 7 days a week.

You know already at what stage of readiness the passenger and high-speed lines are. While the most complicated stage of assembling their track structure is in the preparatory period, construction continues on other areas of the testing and certification center.

The contractors have already completed installing formwork, embedded items for anchor joints and began concreting the foundation plate at the first anchor support on the cargo line. It is planned to fill in 120 cubic meters of concrete today.