Construction Work at the Section of SkyWay Cargo Route

Construction Work at the Section of SkyWay Cargo Route

08 February 2018 2805

Work continues in EcoTechnoPark at the section of the cargo complex. In particular, assembly of the elements for the track structure of the first U-turn are in process — at the moment about 60% of the total number of metal structures are mounted.

Preparatory work is going on at the second U-turn of the cargo line, waterproofing is completed and backfilling is being done with a layer-by-layer compaction of soil into the outside drainage pit of the loading/unloading terminal.

Sergey Zaiko, Director of construction, SkyWay Technologies Co. commented on the current work.