Photo report from EcoTechnoPark of March 16

16 March 2016 837

Designer supervision. Control of accepting concrete mixture for stiffness diaphragms on the first floor. Checking the accompanying documentation on the concrete mixture. Filling of concrete cubes for subsequent strength tests in the laboratory. Pouring concrete in pylons on the right side of the first floor of the transport and logistics hub. Fabrication of elements for intermediate supports of the SkyWay intellectual fencing with the following assembly of intermediate and anchor supports for the intellectual fencing and stretching of the string fencing system. According to preliminary estimates, the complex installation of the SkyWay fencing will take about a month.